Joint Rig Committee Renewables Code of Practice, Renewables Scope of
Work and
Renewables Certificate of Approval Requirements and Examples
Joint Rig Committee
Marine Warranty Surveyors’ Code of Practice
(COP)
The purpose of this
COP
is to:
a.
clarify the
roles of the Marine Warranty Surveyor (MWS), assured and underwriters in the performance and specification of a Marine
Warranty survey;
b. establish agreed standards
for the attending MWS when conducting a survey;
c. define the lines
of
communication between underwriters and the MWS;
d.
establish agreed qualifications for the attending
MWS when conducting a survey;
e.
where applicable, outline the basic requirements for the Certificate(s) of Approval (COA) and establish the definition of “first in series” as detailed in the JRC MWS COA Requirements section below.
Nothing in this COP shall relieve any party of any
legal obligations existing in the absence of this document and nothing contained in this COP shall take precedence over any provisions of the Policy.
This Code of Practice has been produced to accompany
the attached Joint Rig Committee Scope of Work (SOW). A tailored
Project Specific Scope of Work (PSSOW) may be substituted with the explicit prior agreement of underwriter(s).
1. The Role of the MWS
1.1
The fundamental objective of the MWS is to make reasonable endeavours to ensure that the risks associated with the warranted
operations to which a Marine Warranty Surveyor is appointed are reduced to an acceptable level, in accordance with best industry
practice.
1.2
The MWS Company will ensure that any individual MWS appointed to sign a COA in accordance with the SOW:
1.2.1
is appropriately accredited by the Society
of Offshore Marine Warranty
Surveyors (SOMWS); or
1.2.2
can demonstrate competence by completing document JRC MWS Information Form (JR2019-009) or the latest
version that is available in the Technical
Documents tab section
of the JRC webpage (www.lmalloyds.com/jointrig) to the
satisfaction of underwriters,
prior to commencing the activities.
1.3
The Marine Warranty Surveyor will issue a COA for each critical
operation as defined in the relevant
scope of work, provided that they are satisfied, so far as possible, that the operations
are conducted in accordance with:
1.3.1 recognised codes of practice for
design and operations;
1.3.2
best industry practice appropriate for the vessel(s), equipment and location(s);
1.3.3
vessel(s) and equipment being used within defined safe operating limits; and
1.3.4
the most current Marine Operations Manual available for the project; (Note: When an operation is conducted
outside the Marine
Operations Manual, this shall be subject to a formal Management of Change process, with senior leadership, technical authority and MWS approval.)
1.3.5
the MWS must be satisfied with work undertaken by other third party MWS (e.g. for any vessel).
1.4
Upon request the MWS shall propose
an MWS plan to be agreed
by the assured and underwriters which indicates, as a minimum,
each activity, milestones, attendances and issuance
of
COA(s) for the project.
1.5
Upon request the MWS will
make available to underwriters:
1.5.1
an opinion on the adequacy of the SOW – if there are any gaps or omissions this should be communicated to the Assured
and the SOW updated accordingly;
1.5.2 a
schedule of actual,
proposed and repeat site attendances; and
1.5.3 a
schedule of COAs
to be
issued.
1.5.4 COA requirements
The number of COAs required are as
follows:
1.5.4.1
For WTG Foundation installation COAs shall be issued for 20% of all foundations of the same design and/or installation method. Different installation methods include drive vs drill/drive, different design includes a variance
of more than 15 metres in the overall
length of the foundation, or changes in the design of secondary
steel work for different vessel embarkation approaches.
1.5.4.2
For WTG topside installation COAs shall be issued for 20% of all WTGs.
1.5.4.3
Every OSS foundation and topside installation shall have a separate COA issued.
1.5.4.4
For Inter Array Cable laying COAs shall be issued for 20% of all cables.
1.5.4.5
Every Export cable installation shall have a separate
COA issued.
1.5.4.6
Every cable joint shall have a separate COA
issued.
1.5.4.7 For Floating Offshore Wind, every unit will have a COA issued.
The above requirements are also applicable to decommissioning activities.
1.6
The MWS will:
1.6.1
advise underwriters when a confidentiality agreement with the assured is in place which would preclude
the exchange of information or communication
with underwriters; and
1.6.2
notify underwriters of any conflicts of interest. Examples of services that could present a conflict
of interest with the Marine
Warranty work, include:
1.6.2.1
Marine or Design Consultant (or equivalent)
involved in:
a.
Design of project components to be used in a marine operation, the failure
of which could compromise the integrity of a Project
asset (for example a lift beam or padeye);
b. Primary analysis of structures, hulls or component parts thereof; (Note: The Marine Warranty Surveyor
is, however, expected to
review a design by others
where this has a direct bearing on the marine risk e.g. check the lift analysis
of turbine components.)
c. The production of procedures, project standards, risk assessments and other management documentation which influences how a marine operation
is conducted and which any activity
that has a direct bearing
on
the risk of a particular marine operation e.g. loadout, transportation, lift operations;
1.6.2.2
Loss Adjusting;
1.6.2.3
Verification services associated with the operation; and
1.6.2.4
Rig Moving (if required
or used
for a renewables project).
1.7
The MWS will immediately
advise underwriters, with a copy to the
assured:
1.7.1
if any COA is withheld, or a Non-Conformance Certificate issued. Reasons for
this should
be clearly stated. Examples
include:
1.7.1.1
failings of the documentation
provided;
1.7.1.2 failings in the preparations
made;
1.7.1.3
unacceptable change of circumstances which depart from the
approved procedures and preparations at any point up to
the planned issuing of a COA;
1.7.1.4
a proposed operation that is considered too dangerous
to be considered as acceptable good practice from the outset or as preparations proceed, e.g. where weather conditions deteriorate to the point that they exceed the limits for a defined safe operation
as agreed
by the MWS;
1.7.2
if the assured
fails to comply with any recommendations made by the
MWS;
1.7.3
of any proposed changes to
relevant key personnel
employed by the MWS company.
1.8
The MWS shall inform
underwriters of any:
1.8.1
access restrictions to a site or work place of any item or activity
to be warrantied; and
1.8.2
continued lack of information for a warrantied event that cannot or will not be resolved on site but which may prevent
the eventual approval of an operation;
1.9
The MWS shall agree suitable lead times for attendance at vessel / site and documentation release with the assured.
1.10
The MWS may use information available from verifiable sources to assist
with the
conduct of the Marine
Warranty activities. Where such information is relied upon by the MWS it should be clearly
referenced within the MWS Progress Report
2. Role of the Assured
2.1.
The Assured must ensure that the selected
MWS Company is suitably qualified to
perform Marine Warranty activities in accordance with this COP and associated SOW (or PSSOW as
applicable). Qualification of the MWS company shall be as per the JRC MWS Companies Pre-Qualification & Good Practice Guideline (JR2019-010 or latest version available in the Technical
Documents tab
of JRC webpage (www.lmalloyds.com/jointrig)) or an equivalent process demonstrated by the assured
to underwriters.
2.2.
Once appointed on the project,
the MWS Company
shall not be changed without the express
and
prior agreement of underwriters.
2.3.
The assured shall:
2.3.1.
provide the MWS with a point of contact
for underwriters and an appropriate point of contact in the assured’s organisation to assist with the resolution of queries within 14 working days following the
appointment of the MWS or prior to commencement of operations, whichever is
sooner;
2.3.2.
provide underwriters with the contact details of the MWS within 14 working days following
the appointment of the
same;
2.3.3.
procure MWS participation at all relevant project management meetings, including the marine operations HAZOP / HAZID / SIMOP, contingency planning and assurance / testing
plans, and at JSA (job safety analysis) meetings before the commencement of each marine operation;
2.3.4.
contract the
MWS company directly (without
the involvement of any contractor or intermediary) unless required to enable
compliance with
the law in the jurisdiction
or government regulations;
2.3.5.
provide reasonable access and transportation facilities to allow the MWS to perform
the necessary work;
2.3.6. formally acknowledge receipt of all recommendations from the MWS;
2.3.7.
maintain a
record of compliance with and deviations from such recommendations;
2.3.8.
obtain written approval from the MWS for any such deviation(s); and
2.3.9.
agree and comply with suitable
lead times agreed with the MWS, in conjunction with item 1.10.
3.
Role of the Underwriter
3.1.
The Panel of MWSs is to be agreed by underwriters in conjunction with the JRC MWS Companies Pre-Qualification & Good Practice
Guideline (JR2019-010 or latest version available in the Technical
Documents tab of JRC webpage (www.lmalloyds.com/jointrig)).
3.2.
Other additions to the panel will need to demonstrate their capability/experience of similar projects and water depths, and to be agreed by underwriters.
3.3.
On each project, underwriters will specify whether a “kick off” meeting
is required between underwriters, the assured and the MWS. The assured, underwriters and MWS shall agree key risk milestones and date(s) for a joint review of the project
scope and development and the MWS SOW should be updated to reflect any agreed changes and
disseminated.
3.4.
At the request of the MWS, underwriters will make available:
3.4.1. relevant applicable
policy terms
and conditions
including, in particular, any warranty
provisions or conditions
precedent; and
3.4.2.
identity and contact details (including telephone, e–mail, fax and out of hours numbers) of the nominated
underwriter to receive communications
from the MWS.
4. MWS Progress Report
4.1.
Where requested, the MWS shall issue a monthly
report to underwriters directly.
4.2.
The report shall include
the following contents:
4.2.1.
Introduction (executive summary; report No.; project start date; project end date; and name
of individual performing
the survey);
4.2.2.
Progress (activities performed in the last period and activities to be performed in the next period);
4.2.3.
Summary of documentation reviewed (table
showing number of documents reviewed in the last period,
number approved, number on hold and documents reviewed for information only. The document register can be attached
showing document status as an appendix);
4.2.4. Attendances:
- Meetings – date, location,
purpose;
- Surveys – date, vessels, location, name of MWS;
-
Site attendances – date, location, purpose, number of repetitive site attendances;
- List of all COAs
issued since the previous report);
4.2.5.
Invoicing (progress against CTR (Cost, Time, Resource) sheets with value of work done to report date and latest estimate of expenditure to the end of activities together with a commentary on significant deviations from the original
estimates; variation orders; and the total invoiced);
4.2.6. Areas of concern (technical, project management and invoicing); and
4.2.7. Safety (incidents reported, lost
time incidents, statistics, etc.).
5.
MWS Site Survey Reports
5.1 The MWS’s report
shall:
5.1.1
include the
name of the individual performing the survey and survey location;
5.1.2
state, where necessary, recommendations which are required
for the issuance of any COAs, expressed in writing in a clear and explicit manner and
capable of verifiable implementation.
JRC Renewables Scope
of Work (SOW)
The following summarises the Certificates of Approval (COA) required to be issued by the MWS
at site prior to
the commencement of
each of the specified activities:
Offshore wind installations
are usually categorised as
follows:
·
Foundations
These can be piled jackets,
monopiles, Gravity Based Structures (GBS), suction caissons or floating structures. All may, or may not, have transition pieces. Fixed structures can be installed
from a jack-up or floating
Heavy Lift
Vessel (HLV).
·
Wind Turbine Generators (WTG)
These typically consist of tower sections, nacelles, hubs and blades and are typically
installed using jack-ups.
·
Inter Array Cables
These can be supplied
in a continuous length or cut to length, in addition to laying, the pull-ins
are complex and the burial
operations, together with any rock protection, comes with risks.
·
Export cables
Depending on the length
these may require joints and will also require beach pull-ins, sometimes
through HDDs and platform pull-ins
followed by burial.
·
Offshore Sub-Stations (OSS)
These transformer platforms can be installed
on a regular
platform jacket together with associated topside installations. Sometimes the foundation can be a monopile
or a GBS. The guidance
for OSS is also applicable to High Voltage Direct Current (HVDC) converter platforms which may be separate installations.
For each of the above categories the following
major marine activities (and issuing of COAs)
takes place:
·
Loadouts.
·
Towage, transportation and offshore
transfer (if required).
·
Installation of WTGs (fixed and floating), nacelles, rotor assembly (taken to mean blades and hub), jackets or monopiles (for Offshore Sub-Stations – OSS) and associated foundations, topsides for the Offshore Sub Station (OSS) platform, cable and subsea connections and foundations (including piling) for the
WTG’s and jackets
or monopiles
for transformers.
·
Cable loading and offloading.
·
Cable ship/barge sailaway or other suitable
marine transport.
·
Cable laying (covering
trenching and burial).
·
Start-up, crossings and tie-ins.
·
Shore approach/pull-ins/Horizontal Directional Drilling (HDD).
These activities will also be similar and require a COA for other
renewables projects (wave, current, tidal, solar, hybrid types)
The following table details all the required
activities (reviews, independent checks and calculations, attendances etc.) and specific conditions that may apply associated with
the above COAs.
Where this SOW does not adequately cover the operation(s) required the JRC Upstream Construction SOW
(JR2019-006) should be
referred to.
This document contains the SOW intended
to be used with the JRC Renewables Marine Warranty Survey Endorsement (JR2020-030A).
Definition of Renewables:
Renewables are defined,
for the purposes of this SOW,
as being Marine Operations (loadout, transportation or installation) which are of a medium
to high
level of complexity including marine operations
for
offshore wind farms, involving structures, including
fixed and floating foundations, transition
pieces, towers, nacelles and rotor assemblies, inter array cables and
export cables, OSS platforms and
foundations, and HVDC converter platforms and
foundations (if applicable).
The engineering and
analysis required for Renewable marine
operations would be significant and specific
to the marine operation in question and require the use of specialist software and professionally qualified engineering
personnel.
In addition
to WTGs, this SOW will also apply
to wave,
current, tidal, hybrid
types of renewables
or
other forms of renewable
energy installations.
Scope of Work (SOW) 1:
General Activities applicable
to all sections
The activities required
by this section relate to all
sections. During attendance for a specified operation, the Marine
Warranty Surveyor (MWS) is to check compliance with all relevant documents
approved. The MWS is to check that all recommendations have been closed
out
with respect to vessels
agreed to be fit
for purpose. The MWS
is
to also check that all
critical actions required as
per Hazop, Hazid and SIMOPS
have been addressed prior to
issuing the associated COA.
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Master Document Register |
X |
|
Metocean criteria, including: -
Limiting seastate -
Wind -
Loop, eddy,
river and tidal
currents -
Ice formation
and ice loading -
Met-ocean windows for all marine
operations |
X |
|
Weather forecasting procedures |
X |
|
Independent weather and met ocean
forecasting including (loop, eddy,
river and tidal
currents) for
all marine operations
for the issuing of COAs |
X |
|
Project details/schedule |
X |
|
Standards, design codes and recommended practices for marine operations
in accordance with good industry practice |
X |
|
Request evidence that the project is using
an approved Integrated Management
System to control
documents and the QA/QC for a project including all marine
operations |
X |
|
Management of Change
(MoC) procedures |
X |
|
Third Party Verification (if required): -
Foundation
washout -
Vessel interface (for DP thruster action
scour) -
Geotechnical interface (piling) |
X |
|
Project Communications and Interfaces |
X |
|
Weight reports, CoG (and gyradius) and weight contingency factors |
X |
|
Procedures for use of installation vessels (WTG and foundation installation vessels
and cable layers)
and equipment including pile hammers, cable laying and trenching equipment, grouting equipment etc. |
X |
|
Loadout Manual(s) including ballast
plan, moorings, quay strength, vessel strength, seafastening and intact
and damaged stability (for
all incremental stages). |
X |
|
Installation manuals describing all
aspects of the installation for
WTG’s and their
foundations, jackets, piling, cable laying, cable tie-ins, cable crossings, pull-ins of cable, 1st and 2nd end pull-ins, cable jointing and cable burial. |
X |
|
Installation manuals describing all aspects of the installation for wave, current, tidal or solar installations including all periphery activities such as cable
laying and foundations installation |
X |
|
Suitability surveys of all vessels required for an operation (including installation vessels, jack-ups, HLV’s, cable laying
vessels, trenching vessels, equipment (including for burial), walk
to work vessels, Pre-Lay Grapnel Run (PLGR) vessels, where appropriate, refuelling vessels, rock placement vessels, dredgers etc.) (It is acknowledged that for break bulk or partial
cargoes a full survey and report may prove to be impractical due to vessel turnaround time and availability, especially if the vessel operates on a liner service.
In which case the surveyor is to be satisfied as to the general
seaworthiness and suitability of the vessel.) |
X |
X Issue report confirming vessel is suitable |
Tug Suitability Survey - Tug (including manoeuvring tugs) suitability survey and approval -
Confirm valid Class certificate, with
no outstanding conditions of class
(or agree all outstanding conditions of Class
are not material to the intended operations.) -
Valid bollard pull test certificate -
Redundancy of systems -
Crew competency proven and valid
training records -
Communications |
X |
X |
Towage Equipment Suitability Survey - Towing equipment certificates validity prior to tow -
Current towing equipment (and NDT inspection certificates as appropriate) prior to tow (comment on adequacy and frequency) -
Towing wire certification validity prior
to tow -
Towing arrangement (equipment
and wire design and installation1 Design of towing systems for anticipated environmental forces shall be in accordance with
recognised industry standards (e.g. the relevant section(s) of ISO19901-6) |
X |
X |
Transportation vessel/
loading and unloading equipment - Confirmation of suitability of transportation vessel -
Confirmation that the transportation Vessel
has a valid IACS Class certificate, and is class maintained (with no conditions of class) (or agree
all outstanding conditions
of Class as not being material to the intended operations.) -
Valid loadline certificate -
Relevant valid ISM and SOLAS
certification -
Verification of the adequacy and structural strength of the cribbing and
sea fastenings -
Confirmation good working
order of all operational equipment and machinery required for
loading and unloading operations (including contingency items) -
Seaworthiness and water-tight integrity |
X |
X |
Installation vessel: -
Confirmation of suitability of installation vessel -
Confirmation that the transportation vessel
has a valid IACS
Class certificate and is class maintained (with no Conditions of Class)
(or agree all outstanding Conditions of Class as not being material to the intended operations) -
Valid Loadline Certificate -
Relevant valid ISM and SOLAS
certification |
X |
X |
-
Verification of the adequacy and structural strength of the cribbing and seafastenings -
Confirmation that all operational equipment and machinery required for installation operations (including contingency items) is in good
working order -
Confirmation that all lifting
installation equipment is certified, for the relevant tonnages to be lifted -
Seaworthiness and watertight
integrity |
|
|
Voyage /Towage
Manual(s) including: -
Bollard pull
requirements -
Configuration of tugs -
Vessel strength -
Intact and damaged stability -
Voyage details -
Contact information -
Pre-voyage Tow Plan and Risk Assessment -
Route Planning
(incl. sea room, safe
havens and refuelling) -
Hazard identification -
Trim and stability - ability to withstand environmental forces (wind, wave, current) -
Weather routing -
Confirm that the MOU (installation jack-up) has a valid Class certification without Conditions of Class (or agree all outstanding conditions of Class
are not material to the intended operations.) -
Valid loadline certificate -
Relevant valid ISM and SOLAS
certification -
Fuel requirements (contingency) -
Communications (Reporting
Protocols) and language restrictions -
Manning levels justified -
Riding crew (including Towmaster) competency proven and valid
training records -
Navigational Aids (Navaids) -
Tow routes/passage plans and safe
havens including: · Checking underkeel clearances ·
Side and overhead clearances for all movements ·
Planned contingency movements ·
Review of
surveys
of
final
and contingency locations |
X |
X Check Compliance |
Contingency Planning for Emergencies -
Bunkering -
Line parting,
availability of spare
tow line, rigged reconnection equipment and adequate sea room -
Emergency survival
anchor and deployment method in event
of tow failure close
to shore -
Availability of additional vessels -
Tug equipment
failure -
Engine failure -
Heavy weather/storm approach, including safe approach to shore/safe haven -
Grounding -
Collision -
Fire and explosion -
Damage stability -
Water ingress through valves |
X |
|
-
Structural failure -
Riding crew evacuation -
Key equipment breakdown (critical spares) -
Emergency in-line joint
repair plan -
Replacement cable availability -
Sufficient spare marine joints - Qualified jointing team |
|
|
Positioning including verification of positioning requirements, anchoring and mooring calculations, DP requirements including FMEA, DP testing
requirements |
X |
X |
Confirmation of verification of design and Class or build quality where class not
confirmed |
X |
|
HUC and Project handover |
X |
|
Sufficiency of data
acquisition and testing for
soil/rock mechanics and geotechnical parameters for
foundations at proposed locations until completion of installation |
X |
|
Adequacy of structures to withstand loads during loadout, tow/transportation, lifting, mating and installation operations |
X |
|
Cranes and lifting equipment details
including Certificates and Inspection Records |
X |
|
Main and emergency towing equipment details and connection points1. |
X |
X |
Marine Hazid, marine Hazop and SIMOPS |
X |
X |
Confirm adequacy and on-site
integrity (and
acceptable functioning) of sea-state monitoring equipment |
X |
X |
Prototypical and Step-Out Technology Items (any
items that may have an effect
on MWS approved activities - temporary or permanent phases): -
Qualification of items -
Testing of items -
Assurance
of performance and reliability |
X |
X |
X Denotes activity to be performed
Notes for 1. General Activities
1.
Visual inspection and confirmation that the actual tow arrangement is fully consistent with the tow arrangement drawings(s) and
specifications. Confirm
all relevant certificates in date.
Notes applicable to all sections:
·
MWS shall only issue COAs for operations they physically attend.
·
MWS activities to be carried out independently of Class attendance/requirements.
·
MWS to use a recognised industry standard (e.g. the relevant section(s)
of ISO19901-6) as minimum standards
in the execution of this
SOW or a clearly
defined set of standards
agreed by Underwriters.
Scope of Work (SOW) 2:
Fixed Bottom Offshore Wind Farm (WTGs
foundations, WTGs, OSS
foundations, OSS topsides)
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
1. WTG foundations |
|
|
|
1.1 Fabrication and Loadout |
|
|
|
Loadout Procedures Manual: Trailered/skidded/lifted etc. |
X |
X Check Compliance |
|
Motive power systems (trailers, SPMTs etc.) |
X |
|
|
Structural strength of skidding system or trailers for required operation |
X |
|
|
Quayside Capacity for Load |
X |
|
|
Link beam/bridge design |
X |
|
|
Rigging and lift point
design |
X |
|
|
Capability and certification of cranes |
X |
|
|
Grillage structural checks |
X |
|
|
Water depth, tidal
limitations |
X |
|
|
Certification of all loadout equipment |
X |
|
|
Emergency contingency plans |
X |
|
|
Ballast system trials |
X |
X |
|
Loadout operation
(tide, ballasting and Loadout operational limitations) |
X |
X |
X |
As-built dimensions of foundation / WTG/ transition piece (if applicable) interfaces |
X |
|
|
1.2 Transportation to project site |
|
|
|
Loadout plan: -
Fabrication yard or marshalling harbour to site -
Vessel transfer (if required) |
X |
|
|
Transfer of foundation from
transportation vessel to installation vessel (if required) |
X |
X |
|
Transportation/Towing Manual |
X See SOW 1 for
details |
|
|
Procedure for departure (including draught, tidal, environmental limits) |
X |
|
|
Motion response analysis |
X |
|
|
Grillage, seafastening, cribbing and Lashing design, including fatigue
design considerations (inc. NDT requirements) |
X |
X |
|
Firefighting, lifesaving and emergency equipment for manned
tows |
X |
X |
|
Emergency anchors and mooring including, mounting and release system. |
X |
|
|
Internal seafastenings/voyage protection |
X |
X |
|
Self-propelled ships lashings and securing |
X |
X |
X |
Intact and Damaged
Stability |
X |
|
|
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Review and approve transportation routes, weather windows and safe
havens using a suitable marine transportation method or software appropriate to the voyage |
X perform independent assessment |
|
|
Transportation -
Mooring system -
Jacket structure (if applicable) -
Jacket subsea
template (if applicable) |
X |
X Attend Sailaway |
X Issue COA for Sailaway |
Anti-Piracy Measures |
X |
|
|
Mooring adequacy on arrival to withstand Natural Hazard exposure for both temporary and long-term moorings |
X |
|
|
1.3 Installation |
|||
As installation configurations and techniques vary significantly, notwithstanding the requirements in the section below
where there
are discrete offshore installation operations with possible hold points
between each of these
operations, COAs are required for the commencement of each of these operations. |
|||
Foundation
design: -
Monopile
and transition piece -
Jacket/platform -
Suction caisson -
Gravity Based Structure
(GBS) |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Installation procedure (version reviewed and approved by MWS) at site. |
X |
X Check Compliance |
|
Site/seabed survey and water depth |
X |
|
|
The vessel integrity assessment by comparison of the location with
the vessel Marine Operating
Manual should have the following (where applicable): -
Spudcan penetration (MN v metres), demonstrated on a leg penetration curve -
Reserve leg length -
Preload capacity -
Air-gap
adequacy -
Anchoring and mooring suitability Additionally, the assessment must confirm that the location specific data
is less onerous than that
used as the design
basis in the vessel Marine Operating Manual, so that for example, leg,
chock, pinion, anchor and mooring system strength is adequate. If the target location is found
to be unsuitable the above
assessment shall
be carried out for the new location. Further, where leg
extraction problems are predicted, a warning should
be included as part of the assessment. |
X |
|
X |
Jack-up and jack-down procedure (if applicable) |
X |
X Attend first jack-up and first jack- down of campaign |
X |
Crane suitability: |
X |
X |
|
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Crane(s) to be inspected prior
to lifting operations taking place. The inspection shall include but not be limited
to: - Crane certification and Vessel Class - Operating history - Maintenance and repair records for crane and marine systems An
external visual
examination of the crane(s) and vessel. |
|
|
|
Temporary Installation aids including: - - Lift points -
- Lifting
aids -
- Bumpers
and Guiding Systems - - Positioning systems, etc. |
X |
X |
|
Static and dynamic
hook load calculations (single and dual crane
lifts) including considerations for lifting
through water. The independent calculations performed shall include environmental limitations and be in accordance with
the approved crane(s) curves. All lifting factors shall
be approved by MWS |
X |
|
|
Installation vessel position, monitoring and control |
X |
X |
|
Foundation
Installation: - Foundation launch
operation -
Foundation
upending -
Foundation
lift (Strength Check verifying capability of withstanding installation forces including Hydrostatic Collapse Checks for leg collapse and checks on single compartment damage stability) |
X |
X |
X See section 1.5 regarding first in series COA to be provided for and prior to sequence of irreversible operations |
As-built dimensions of foundation/WTG interfaces |
X |
|
|
Piling operations including calculations, analysis and Installation Manuals |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Foundation/transition piece/platform connection including: -
System integrity -
Grouting operations
(if applicable) - Confirmation of grout
strength (if applicable) - Testing of grouting pumps under full load (if applicable) |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Cathodic protection
system installation |
|
|
|
Scour protection installation |
|
|
|
Hook-up and commissioning |
X |
X |
|
2. WTGs |
|
|
|
2.1 Fabrication and Loadout |
|
|
|
Loadout Procedures
Manual: lifted
etc. |
X |
X Check Compliance |
|
Motive power systems (trailers, SPMTs etc.) |
X |
|
|
Structural strength of trailers for required operation |
X |
|
|
Quayside capacity
for load |
X |
|
|
Link beam/bridge design |
X |
|
|
Rigging and lift point
design |
X |
|
|
Capability and certification of cranes |
X |
|
|
Grillage structural checks |
X |
|
|
Water depth, tidal
limitations |
X |
|
|
Certification of all loadout equipment |
X |
|
|
Emergency contingency plans |
X |
|
|
Ballast system trials |
X |
X |
|
Loadout operation
(tide, ballasting and Loadout operational limitations) |
X |
X |
X |
As-built dimensions of foundation / WTG interfaces |
X |
|
|
2.2 Transportation to project site |
|
|
|
Loadout plan: -
Fabrication yard or marshalling harbour to site -
Vessel transfer (if required) |
X |
X Check Compliance |
|
Transfer of WTG from
transportation vessel to installation vessel (if required) |
X |
X |
|
Transportation / towing manual |
X See SOW 1 for
details |
|
|
Procedure for departure (including draught,
tidal, environmental limits) |
X |
|
|
Motion response analysis |
X |
|
|
Grillage, seafastening, cribbing and Lashing design, including fatigue
design considerations (inc. NDT requirements) |
X |
X |
|
Firefighting, lifesaving and emergency equipment for manned
tows |
X |
X |
|
Emergency anchors and mooring including, mounting and release system. |
X |
|
|
Internal seafastenings / voyage protection |
X |
X |
|
Self-propelled ships lashings and securing |
X |
X |
X |
Intact and Damaged
Stability |
X |
|
|
Review and approve transportation routes, weather windows and safe
havens using a suitable marine transportation method or software appropriate to the voyage |
X perform independent assessment |
|
|
Transportation -
Turbine towers -
Turbine nacelles -
Turbine rotor assembly (components transported to site on installation vessel or barge) -
Turbine transformers (if located
on transition
piece) |
X |
X Attend Sailaway |
X Issue COA for Sailaway |
Anti-Piracy Measures |
X |
|
|
Mooring adequacy on arrival to withstand Natural Hazard exposure for both temporary and long-term moorings |
X |
|
|
2.3 Installation |
As installation configurations and techniques vary significantly, notwithstanding the requirements in the section below
where there
are discrete offshore installation operations with possible hold points
between each of these
operations, COAs are required for the commencement of each of these operations. |
|||
Installation procedure (version reviewed and approved by MWS) at site. |
X |
X Check Compliance |
|
Site/seabed survey and water depth |
X |
|
|
The vessel integrity assessment by comparison of the location with
the vessel Marine Operating
Manual should have the following (where applicable): -
Spudcan penetration (MN v metres), demonstrated on a leg penetration curve -
Reserve leg length -
Preload capacity -
Air-gap
adequacy -
Anchoring and mooring suitability Additionally the assessment must confirm that the location specific data
is less onerous than that
used as the design
basis in the vessel Marine Operating Manual, so that for example, leg,
chock, pinion, anchor and mooring system strength is adequate. If the target location is found
to be unsuitable the above
assessment shall
be carried out for the new location. Further, where leg
extraction problems are predicted, a warning should
be included as part of the assessment. |
X |
|
X |
Jack-up and jack-down procedure (if applicable) |
X |
X Attend first jack-up and first jack- down of campaign |
X |
Crane suitability: Crane(s) to be inspected prior
to lifting operations taking place. The inspection shall include but not be limited
to: - Crane certification and Vessel Class - Operating history - Maintenance and repair records for crane and marine systems An
external visual
examination of the crane(s) and vessel. |
X |
X |
|
Turbine installation: -
Lower tower section
fitted to Transition Piece/foundation -
Middle/upper tower section assembly -
Nacelle -
Rotor assembly (e.g.
connect first two blades as “bunny ears” to nacelle, then
connect third
blade) |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Temporary power solution (if WTG installed prior to Grid connection) |
X |
|
|
Hook-up and commissioning |
X |
X |
|
3. Offshore Sub Station (OSS) Foundation |
|||
3.1 Fabrication and Loadout |
|||
Loadout Procedures Manual: Trailered/skidded/lifted etc. |
X |
X Check Compliance |
|
Motive
power systems (trailers, SPMT’s etc.) |
X |
|
|
Structural strength of skidding system or trailers for required operation |
X |
|
|
Quayside Capacity for Load |
X |
|
|
Link beam/bridge design |
X |
|
|
Rigging and lift point
design |
X |
|
|
Capability and certification of cranes |
X |
|
|
Grillage structural checks |
X |
|
|
Water depth, tidal
limitations |
X |
|
|
Certification of all loadout equipment |
X |
|
|
Emergency contingency plans |
X |
|
|
Ballast system trials |
X |
X |
|
Loadout operation
(tide, ballasting and Loadout operational limitations) |
X |
X |
X |
As-built dimensions of foundation / module interfaces |
X |
|
|
3.2 Transportation to project site |
|
|
|
Transportation/Towing Manual |
X See SOW 1 for details |
|
|
Procedure for departure (including draught, tidal, environmental limits) |
X |
|
|
Motion response analysis |
X |
|
|
Grillage, seafastening, cribbing and Lashing design, including fatigue
design considerations (inc. NDT requirements) |
X |
X |
|
Firefighting, lifesaving and emergency equipment for manned
tows |
X |
X |
|
Emergency anchors and mooring including, mounting and release system. |
X |
|
|
Internal seafastenings / voyage protection |
X |
X |
|
Self-propelled ships lashings and securing |
X |
X |
X |
Intact and Damaged
Stability |
X |
|
|
Review and approve transportation routes, weather windows and safe
havens using a suitable marine transportation method or software appropriate to the voyage |
X perform independent assessment |
|
|
Transportation -
Piles -
Jacket structure -
Jacket subsea template -
OSS Transition Piece
(TP) and associated
secondary steelwork (ladders, J tubes, etc) -
OSS topside |
X |
X Attend Sailaway |
X Issue COA for Sailaway |
Anti-Piracy Measures |
X |
|
|
Mooring adequacy on arrival to withstand Natural Hazard exposure for both temporary and long term
moorings |
X |
|
|
3.3 Installation |
|
|
|
As installation configurations and techniques vary significantly, notwithstanding the requirements in the section below
where there
are discrete offshore installation operations |
with possible hold points
between each of these
operations, COAs are required for the commencement of each of these operations. |
|||
Installation procedure (version reviewed and approved by MWS) at site. |
X |
X Check Compliance |
|
Site/seabed survey and water depth |
X |
|
|
The vessel integrity assessment by comparison of the location with
the vessel Marine Operating
Manual should have the following (where applicable): -
Spudcan penetration (MN v metres), demonstrated on a leg penetration curve -
Reserve leg length -
Preload capacity -
Air-gap
adequacy -
Anchoring and mooring suitability Additionally the assessment must confirm that the location specific data
is less onerous than that
used as the design
basis in the vessel Marine Operating Manual, so that for example, leg,
chock, pinion, anchor and mooring system strength is adequate. If the target location is found to be unsuitable the above assessment shall
be carried out for the new location. Further, where leg
extraction problems are predicted, a warning should
be included as part of the assessment. |
X |
|
X |
Jack-up and jack-down procedure (if applicable) |
X |
X Attend first jack-up and first jack- down of campaign |
X |
Crane suitability: Crane(s) to be inspected prior
to lifting operations taking place. The inspection shall include but not be limited
to: - Crane certification and Vessel Class - Operating history - Maintenance and repair records for crane and marine systems An
external visual
examination of the crane(s) and vessel. |
X |
X |
|
Temporary Installation aids including: -
Lift points - Lifting aids - Bumpers and Guiding Systems - Positioning systems, etc. |
X |
X |
|
Jacket on-bottom stability including mud mat design |
X |
|
|
Static and dynamic
hook load calculations (single and dual crane
lifts) including considerations for lifting
through water. The independent calculations performed shall include environmental limitations and be in accordance with
the approved crane(s) curves. All lifting factors shall
be approved by MWS |
X |
|
|
Installation vessel position, monitoring and control |
X |
X |
|
Jacket Installation: -
Jacket launch operation - Jacket upending - Jacket lift (Strength Check verifying capability of withstanding installation forces including Hydrostatic Collapse Checks for leg collapse and checks on single compartment damage stability) |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
As-built dimensions of jacket/module interfaces |
X |
|
|
Piling operations including calculations, analysis and Installation Manuals |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Grouting including: -
System Integrity - Grouting operations - Confirmation of grout
strength Testing of grouting pumps under full
load for sufficient duration to reflect offshore conditions |
X |
X |
|
Temporary Installation aids including: - Lift points -
Bumpers and Guiding
Systems - Buoyancy tanks and attachment (and removal)
to Jackets (including collapse check and point loading assessment) -
Launch frames -
Positioning systems,
etc. |
X |
X |
|
Deck installation/MSF/module lift/floatover |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Cathodic protection
system installation |
|
|
|
Scour protection installation |
|
|
|
Hook-up and commissioning |
X |
X |
|
4. Offshore Sub Station (OSS) Topside |
|||
4.1 Fabrication and Loadout |
|||
Loadout Procedures Manual: Trailered / skidded / lifted
/ etc. |
X |
X Check Compliance |
|
Motive
power systems (trailers, SPMT’s etc.) |
X |
|
|
Structural strength of skidding system or trailers for required operation |
X |
|
|
Quayside Capacity for Load |
X |
|
|
Link beam/bridge design |
X |
|
|
Rigging and lift point
design |
X |
|
|
Capability and certification of cranes |
X |
|
|
Grillage structural checks |
X |
|
|
Water depth, tidal
limitations |
X |
|
|
Certification of all loadout equipment |
X |
|
|
Emergency contingency plans |
X |
|
|
Ballast system trials |
X |
X |
|
Loadout operation
(tide, ballasting and Loadout operational limitations) |
X |
X |
X |
As-built dimensions of foundation / transition piece interfaces |
X |
|
|
4.2 Transportation to project site |
|
|
|
Transportation/Towing Manual |
X See SOW 1 for details |
|
|
Procedure for departure (including draught, tidal, environmental limits) |
X |
|
|
Motion response analysis |
X |
|
|
Grillage, seafastening, cribbing and Lashing design, including fatigue
design considerations (inc. NDT requirements) |
X |
X |
|
Firefighting, lifesaving and emergency equipment for manned
tows |
X |
X |
|
Emergency anchors and mooring including, mounting and release system. |
X |
|
|
Internal seafastenings/voyage protection |
X |
X |
|
Self-propelled ships lashings and securing |
X |
X |
X |
Intact and Damaged
Stability |
X |
|
|
Review and approve transportation routes, weather windows and safe
havens using a suitable marine transportation method or software appropriate to the voyage |
X perform independent assessment |
|
|
Transportation - OSS Topside |
X |
X Attend Sailaway |
X Issue COA for Sailaway |
Anti-Piracy Measures |
X |
|
|
Mooring adequacy on arrival to withstand Natural Hazard exposure for both temporary and long-term moorings |
X |
|
|
4.3 Installation |
|
|
|
As installation configurations and techniques vary significantly, notwithstanding the requirements in the section below
where there
are discrete offshore installation operations with possible hold points
between each of these
operations, COAs are required for the commencement of each of these operations. |
|||
Installation procedure (version reviewed and approved by MWS) at site. |
X |
X Check Compliance |
|
Site/seabed survey and water depth |
X |
|
|
The vessel integrity assessment by comparison of the location with
the vessel Marine Operating
Manual should have the following (where applicable): -
Spudcan penetration (MN v metres), demonstrated on a leg penetration curve -
Reserve leg length -
Preload capacity -
Air-gap
adequacy -
Anchoring and mooring suitability Additionally, the assessment must confirm that the location specific data
is less onerous than that
used as the design
basis in the vessel Marine Operating Manual, so that for example, leg,
chock, pinion, anchor and mooring system strength is adequate. |
X |
|
X |
If the target location is found to be unsuitable the above assessment shall
be carried out for the new location. Further, where leg
extraction problems are predicted, a warning should
be included as part of the assessment. |
|
|
|
Jack-up and jack-down procedure (if applicable) |
X |
X Attend first jack-up and first jack- down of campaign |
X |
Crane suitability: Crane(s) to be inspected prior
to lifting operations taking place. The inspection shall include but not be limited
to: - Crane certification and Vessel Class - Operating history - Maintenance and repair records for crane and marine systems An
external visual
examination of the crane(s) and vessel. |
X |
X |
|
Temporary Installation aids including: -
Lift points - Lifting aids - Bumpers and Guiding Systems -
Positioning systems,
etc. Requires Close Visual
Inspection and check against design drawings |
X |
X |
|
Static and dynamic
hook load calculations (single and dual crane
lifts). The independent calculations performed shall include environmental limitations and be in accordance with the approved crane(s) curves. All lifting factors shall be approved by MWS |
X |
|
|
Installation vessel position, monitoring and control |
X |
X |
|
OSS topside
Installation: - OSS topside lift - OSS topside installation on OSS foundation (Strength Check verifying capability of withstanding installation forces including Hydrostatic Collapse Checks for leg collapse and checks on single compartment damage stability) |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
As-built dimensions of jacket
/ topside interfaces |
X |
|
|
Grouting (if applicable) including: -
System Integrity -
Grouting operations - Confirmation of grout
strength Testing of grouting pumps under full
load with duration to be agreed to reflect offshore conditions |
X |
X |
|
Temporary Installation aids including: -
Lift points - Bumpers and Guiding Systems - Launch frames - Positioning systems, etc. |
X |
X |
|
Deck installation/MSF/module lift/floatover |
X |
X |
X |
|
|
|
COA to be provided for and prior to sequence of irreversible operations |
Hook-up and commissioning |
X |
X |
|
X Denotes activity
to be performed
Notes applicable to all sections:
· MWS shall only issue COAs for operations that they physically attend.
· MWS activities to be carried
out independently of Class attendance/requirements.
· MWS to
use a recognised industry standard
(e.g. the relevant section(s) of ISO19901-6) as minimum standards in the execution of this SOW or a clearly defined set of standards
agreed by Underwriters.
Scope of
Work (SOW) 3: Floating Foundation Offshore Wind Farm
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
1. Floating WTG |
|
|
|
1.1 Fabrication and Loadout |
|
|
|
WTG/foundation assembly
procedure |
X |
X Check Compliance |
|
Install turbine on floating foundation at quayside |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Static and dynamic
hook load calculations (single and dual crane
lifts) including considerations for lifting
through water. The independent calculations performed shall include environmental limitations and be in accordance with
the approved crane(s) curves. All lifting factors shall
be approved by MWS |
X |
|
|
Crane suitability: Crane(s) to be inspected prior
to lifting operations taking place. The inspection shall include but not be limited
to: - Crane certification and vessel class - Operating history - Maintenance and repair records for Crane and marine systems An external visual
examination of the crane(s) and vessel |
X |
X |
|
Loadout Procedures Manual: Trailered/skidded/lifted etc. |
X |
X Check Compliance |
|
Motive
power systems (trailers, SPMT’s etc.) |
X |
|
|
Structural strength of skidding system or trailers for required operation |
X |
|
|
Quayside capacity
for Load |
X |
|
|
Link beam/bridge design |
X |
|
|
Rigging and lift point
design |
X |
|
|
Capability and certification of cranes |
X |
|
|
Grillage structural checks |
X |
|
|
Water depth, tidal
limitations |
X |
|
|
Certification of all loadout equipment |
X |
|
|
Emergency contingency plans |
X |
|
|
Ballast system trials |
X |
X |
|
Full stability, strength and detailed procedures for foundation load out, including securing info,
ballasting, cribbing and location
details |
X |
|
|
Loadout operation
(tide, ballasting and loadout operational limitations) |
X |
X |
X |
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
As-built dimensions of foundation/WTG interfaces |
X |
|
|
1.2 Transportation |
|
|
|
Transportation / towing manual |
X See SOW 1 for details |
|
|
Procedure for departure (including draught, tidal, environmental limits) |
X |
|
|
Motion response analysis |
X |
|
|
Grillage, seafastening, cribbing and lashing design, including fatigue design considerations (inc. NDT requirements) |
X |
X |
|
Firefighting, lifesaving and emergency equipment for manned
tows |
X |
X |
|
Emergency anchors and mooring including, mounting and release system. |
X |
|
|
Internal seafastenings/voyage protection |
X |
X |
|
Self-propelled ships lashings and securing |
X |
X |
X |
Intact and Damaged
Stability |
X |
|
|
Review and approve tow routes, weather windows and safe havens using
a suitable marine transportation method
or software appropriate to the voyage |
X perform independent assessment |
|
|
Floating out of WTG on integrated buoyancy to moorings |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Towage/transportation -
Floating
WTG towed/transported to site on integrated buoyancy) -
Buoyancy support
for WTG to be towed to site (if
required) |
X |
X Attend Sailaway |
X Issue COA for Sailaway |
Anti-Piracy Measures |
X |
|
|
Mooring adequacy on arrival to withstand Natural Hazard exposure for both temporary and long term
moorings |
X |
|
|
1.3 Installation |
|||
As installation configurations and techniques vary significantly, notwithstanding the requirements in the section below
where there
are discrete offshore installation operations with possible hold points
between each of these
operations, COAs are required for the commencement of each of these operations. |
|||
Installation manual (version reviewed and approved by MWS) at site. |
X |
X Check Compliance |
|
Site/seabed survey and water depth |
X |
|
|
Install turbine mooring system |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Temporary Installation aids including: -
Tow points -
Bumpers and Guiding
Systems -
Buoyancy Tanks and attachment to WTG (including collapse
check and point loading
assessment) -
Positioning systems,
etc. |
X |
X |
|
2. Floating OSS |
|
|
|
2.1 Fabrication and Loadout |
|
|
|
OSS/foundation assembly procedure |
X |
X Check Compliance |
|
Install OSS on floating foundation at quayside |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Static and dynamic
hook load calculations (single and dual crane
lifts) including considerations for lifting
through water. The independent calculations performed shall include environmental limitations and be in accordance with
the approved crane(s) curves. All lifting factors shall
be approved by MWS |
X |
|
|
Crane suitability: Crane(s) to be inspected prior
to lifting operations taking place. The inspection shall include but not be limited
to: -
Crane certification and vessel class -
Operating history -
Maintenance and repair
records for Crane and marine systems An external visual
examination of the crane(s) and Vessel |
X |
X |
|
Loadout Procedures Manual: Trailered/skidded/lifted etc. |
X |
X Check Compliance |
|
Motive
power systems (trailers, SPMT’s etc.) |
X |
|
|
Structural strength of skidding system or trailers for required operation |
X |
|
|
Quayside capacity
for Load |
X |
|
|
Link beam/bridge design |
X |
|
|
Rigging and lift point
design |
X |
|
|
Capability and certification of cranes |
X |
|
|
Grillage structural checks |
X |
|
|
Water depth, tidal
limitations |
X |
|
|
Certification of all loadout equipment |
X |
|
|
Emergency contingency plans |
X |
|
|
Ballast system trials |
X |
X |
|
Full stability, strength and detailed procedures for foundation load out, |
X |
|
|
including securing
info, ballasting, cribbing and location details |
|
|
|
Loadout operation
(tide, ballasting and loadout operational limitations) |
X |
X |
X |
As-built dimensions of foundation/OSS interfaces |
X |
|
|
2.2 Transportation |
|
|
|
Transportation/towing manual |
X See SOW 1 for
details |
|
|
Procedure for departure (including draught, tidal, environmental limits) |
X |
|
|
Motion response analysis |
X |
|
|
Grillage, seafastening, cribbing and Lashing design, including fatigue
design considerations (inc. NDT requirements) |
X |
X |
|
Firefighting, lifesaving and emergency equipment for manned
tows |
X |
X |
|
Emergency anchors and mooring including, mounting and release system. |
X |
|
|
Internal seafastenings/voyage protection/temporary bracing adequacy |
X |
X |
|
Self-propelled ships lashings and securing |
X |
X |
X |
Intact and Damaged
Stability |
X |
|
|
Review and approve tow routes, weather windows and safe havens using
a suitable marine transportation method
or software appropriate to the voyage |
X perform independent assessment |
|
|
Floating out of OSS on integrated buoyancy, to moorings |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Towage/transportation -
Floating
OSS owed to site on integrated buoyancy -
Buoyancy support
for OSS deck to be towed to site (if
required) |
X |
X Attend Sailaway |
X Issue COA for Sailaway |
Anti-Piracy Measures |
X |
|
|
Mooring adequacy on arrival to withstand natural hazard exposure for both temporary and longterm moorings |
X |
|
|
2.3 Installation |
|||
As installation configurations and techniques vary significantly, notwithstanding the requirements in the section below
where there
are discrete offshore installation operations with possible hold points
between each of these
operations, COAs are required for the commencement of each of these operations. |
|||
Installation manual (version reviewed and approved by MWS) at site. |
X |
X Check Compliance |
|
Site/seabed survey and water depth |
X |
|
|
Install OSS platform mooring system |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Temporary Installation aids including: -
Tow points -
Bumpers and Guiding
Systems |
X |
X |
|
-
Buoyancy Tanks and attachment to OSS (including collapse check
and point loading assessment) -
Positioning systems,
etc. |
|
|
|
Install OSS on floating foundation offshore |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Connect OSS, floating out
on integrated buoyancy, to moorings |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Hook-up and commissioning |
X |
X |
|
Scope of Work (SOW) 4:
Subsea Cable Installation and Shore Pull-ins for Fixed and Floating Offshore Wind Farms (inter-array and export cables)
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Fabrication and Load-out |
|||
Cable manufacturing -
Cable design
and basis -
Production principle
and methods |
X |
X |
X |
Factory Acceptance Test
(FAT) after fabrication -
FAT test procedure -
Review of FAT results |
X |
X |
X |
Load-out (reels to be lifted onboard or spooled into a carousel from shore) |
X |
X |
X |
Transportation (see Scope of Work (SOW)
1 for details) |
|||
Transportation by cable layer |
X |
X |
X COA for lashing and securing |
Installation |
|||
Offshore Cable Route review |
X |
|
|
Insured’s project setup -
procedures for preliminary and final cable as built documentation (as laid, as trenched, as buried) -
distribution of updated information to contractors during the construction phase |
X |
|
|
Cable laying (AC
or DC) -
Laying cable on seabed (for
fixed and floating WTG and OSS) -
Installing dynamic cables together with buoyancy modules (for floating WTG or OSS) |
X |
X |
X |
Minimum bend radius - confirm installed radius is within design tolerance |
X |
X |
X |
On-bottom stability, slope stability |
X |
|
|
Trenching and burying
or backfilling, including post-lay checks in accordance with design requirements |
X |
X |
X |
Guard vessels (if applicable) - Review plan for coverage across entire export cable corridor |
X |
|
|
1st and 2nd end pull-ins/connections with WTG and OSS, crossings, spans and shore approaches. |
X |
X |
X |
Termination of cables |
X |
X |
X |
Temporary installation aids, rigging, etc. |
X |
|
|
Infield joints (planned
and unplanned) |
X |
X |
X |
Heavy weather and DP run-off procedures |
X |
|
|
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Vessel manoeuvring, station keeping and cable handling procedures during jointing |
X |
|
|
Hook-up, commissioning and project handover, including all quality and functionality tests on the installed cables, their terminations and joints. |
X |
X |
|
Contingency procedures for recovery of damaged subsea cable, repairing and relaying (if design
permits) |
X |
X |
X (if undertaken as a separate campaign) |
Shore pull-in |
|||
Details
of shore pull-in: -
Trench and drag -
HDD -
Micro tunnelling |
X |
X |
X |
Vessels to be used for shore pull-in |
X |
X |
|
Winches to be used for shore
pull-in |
X |
X |
|
X Denotes
activity to be performed
Notes applicable to all sections:
· MWS shall only issue COAs for operations that they physically attend.
· MWS activities to be carried
out independently of Class attendance / requirements.
· MWS to
use a recognised industry standard
(e.g. the relevant section(s) of ISO19901-6) as minimum standards in the execution of this SOW or a clearly defined set of standards
agreed by Underwriters.
Wave, tide, current and solar installations
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Ship or barge transportations (see Scope of Work (SOW)
1 for details) |
|||
Load out and offload documentation (inc. seafastening design, barge layout
and ballasting) of renewables equipment: -
Wave generator -
Tidal generator -
Current generator -
Solar panels -
A hybrid
arrangement using
one or more of the above
components |
X |
|
|
Loadouts and offloads (inc. trailered / skidded / lifted
/ floated on / etc.)
and seafastenings |
X |
X |
X |
Loadout Pads (for grounded loadouts) |
X |
X |
|
Transportation to site |
X |
X |
X COA for Sailaway |
Install foundation: -
Piling -
Suction piles -
Anchors -
Other |
X |
X |
X COA to be provided for and prior to sequence of irreversible operations |
Voyage Protection |
X |
X |
|
Lifting and setting down/securing at interim locations |
X |
X |
X |
X Denotes
activity to be performed
Notes applicable to all sections:
· MWS shall only issue COAs for operations that they physically attend.
· MWS activities to be carried
out independently of Class attendance / requirements.
· MWS to
use a recognised industry standard
(e.g. the relevant section(s) of ISO19901-6) as minimum standards in the execution of this SOW or a clearly defined set of standards
agreed by Underwriters.
Scope of Work (SOW) 6:
Incidental Decommissioning within renewables projects.
For stand-alone project decommissioning see JRC Decommissioning SOW (JR2019-007)
Activity |
Review &
Approve Procedures / Drawings / Design Calculations |
Attend |
Issue Certificate of Approval (COA) |
Decommissioning documentation including method statements, procedures, Risk Assessments, Hazop, Hazid,
Simops, etc. |
X |
|
|
Anchoring or DP positioning |
X |
X |
|
Commencement of dismantling |
|
X |
X COA for commencement of continuous activity leading
to Sailaway |
Subsea cable removal |
X |
X |
X COA for commencement of continuous activity leading
to Sailaway |
Seafastening / securing and transportation |
X |
X |
X COA for Sailaway |
Offloading at disposal (and
any interim) sites |
X |
X |
X |
Vessel Traffic Management |
X |
|
|
X Denotes
activity to be performed
Notes applicable to all sections:
·
MWS shall only issue COAs for operations that they physically attend.
·
MWS activities to be carried out independently of Class attendance / requirements.
·
MWS to use a recognised industry standard
(e.g. the relevant
section(s) of ISO19901-6) as minimum
standards in the execution of this SOW or a clearly
defined set of standards
agreed by Underwriters.
Abbreviations
A&R Abandon and recovery
CALM Catenary
Anchor Leg Mooring
COA Certificate of Approval
CVI Close Visual
Inspection
DMA Dead man anchor
DP Dynamic Positioning
D/t Diameter / Thickness
DWT Deadweight
FDPSO Floating Drilling Production Storage
and Offloading FGSO Floating Gas Storage and Offloading
FLNG Floating
Liquefied Natural
Gas
FMEA Failure Mode and Effects Analysis
FPF Floating Production Facility
FPS Floating Production System
FPSO Floating Production Storage
and Offloading FPU Floating Production Unit
FSO Floating Storage
and Offloading
FSU Floating Storage
Unit
GBS Gravity
Based Structure
GRT Gross Registered Tonnage
GSOW Generic
Scope of Work
HAZID Hazard Identification
HAZOP Hazard
and Operability
HDD Horizontal Directional Drilling
HLV Heavy Lift Vessel
HUC Hook-up and commissioning
HVDC High Voltage Direct Current
IACS International Association of Classification Societies IMO International Maritime Organisation
ISM International Ship Management (Certificate)
JRC Joint
Rig Committee
JSA Job Safety Analysis
MOPS Mobile Offshore Production Systems
MOU Mobile Offshore Unit
MSF Module
Support Frame
MWS Marine Warranty Survey (or Surveyor)
NDE Non Destructive Examination
NDT Non Destructive Testing
OSS Offshore
Sub-Stations
PLEM Pipeline
End Manifold
PLET Pipeline
End Termination
PLGR Pre-Lay
Grapnel Run
PSSOW Project Specific
Scope of Work QA/QC Quality
Assurance / Quality
Control RFHU Ready For Hook Up
ROV Remotely
Operated Vehicle
RPD Rack Phase Difference
SCR Steel Catenary
Riser
SDU Subsea Distribution Unit
SIMOPS Simultaneous Operations
SOLAS Safety
Of Life At Sea
SOW Scope of Work
SSA Site
Specific Assessment
SUTU Subsea Umbilical Termination Unit
TLP Tension
Leg Platform
TP Transition Piece
UMR Unique Market
Reference
VIV Vortex
Induced Vibration
WTG Wind Turbine
Generator
JRC MWS Certificate
of Approval (COA) Requirements
The Certificate of Approval
(COA) is the final document
in an approval process that includes numerous
activities such as:
- Survey
attendances for suitability and/or condition
of a vessel
- Site assessment and vessel surveys
- Document
reviews and re-reviews
- Site attendance to review preparations
As a result
the COA is not a stand-alone document and the above activities must be referenced to ensure the whole process is completed to the attending
surveyor’s satisfaction with its signing.
Basic Requirements
1.
A COA must only be issued if the surveyor signing
the COA has witnessed
the preparations for the operation and is in attendance at the site. It should be issued immediately prior to the commencement of the operation.
Exception: Location approvals
of MOUs where the COA is issued by the approving office.
The COA should
also be signed by the Assured’s
person in authority
on site (if present) to acknowledge receipt
of the COA and acceptance of the recommendations.
2.
To assure validity
of the COA, approval documentation from the office that performed
the desk top reviews of the operation confirming the acceptability of the documents reviewed
(plans, procedures, calculations etc.) shall be provided
to the attending MWS.
3.
Each COA shall have a unique number.
4.
The title on the COA must be sufficient to identify
the operation being approved.
5.
The MWS’s name shall be printed
underneath the signature.
6.
The time at which the issuing
of the COA has been approved
shall be recorded
and a period of
validity (if issued for first in
series and to cover
a series of events) for the COA must also be recorded.
7.
The original COA shall be given or sent to the Assured with copies retained
by the MWS company.
8.
Traceability of the COA is required by reference to the principal
document(s) approved for the operation.
9.
Where appropriate vessel capacity
(bollard pull, DWT., GRT., displacement etc.) is to be documented to help define a vessel’s suitability for an operation.
10.
For any
COAs issued for the “first in series only”, or a percentage
of components to be installed, this shall be clearly stated on the COA, together with conditions for its issue clearly
stated.
11.
Checklists may be appended to the issued
COA if required to clarify
the scope of the approval.
12.
All recommendations related to the operation must be complied
with prior to the issue of the COA and the COA must not be subject
to any outstanding recommendations. However, any recommendations intended to be complied with after the issue of the COA, as mandated by the MWS, for example
to cover an agreed activity after a tow departs or compliance with a procedures document, shall be specific, measurable, achievable, reasonable, time-bound and clearly listed, attached
to and referenced in the COA .
13.
A UMR (Unique
Market Reference) number is to be provided
on all COAs. This number is available through
the Lead Underwriter insurer and the Assured’s Broker. A UMR is a unique number allocated
to each individual policy.
The UMR will enable clear traceability as to the Policy to which the COA pertains.
Notes:
1. COA for the “first in series only”:
When approval for a repeated operation is required,
for instance, to approve the installation of twenty monopiles, then the operations approved must be identical in all material respects to the first operation otherwise individual COAs are required
for each operation. For instance, the foundation installation method, securing arrangements, vessel ballasting and trim condition, weather window and limiting weather criteria
must all be the same. No additional cargo, change of securing practices, change of route, change of tug, barge or transportation vessel, or other alteration, compared to the initially approved condition,
may be permitted without reference to the MWS. Where the change(s)
are acceptable the MWS must endorse the original
COA or issue a new COA. However,
if multiple tugs, barges
(or other vessels) or equipment
have been approved for use in various combinations with MWS approval, then this is acceptable. If a loss or ‘near miss’ incident occurs during a repeat operation then the COA shall be suspended until the MWS is satisfied that the key root causes have been satisfactorily addressed. For operations involving greater value, loads,
‘at the edge of the envelope', and/or
greater complexity then full attendance is required
and issuance of COA shall be made in each case.
2. Failure
to Issue COA:
If the processes
required for approval are incomplete, then the COA must not be issued.
For example, if approved documentation from the MWS office
performing the desk-top reviews
has not been received
or if recommendations issued by the MWS Office or attending MWS surveyor have not been completed or implemented.
3.
COAs which, after issuing,
no longer conform
to the operation originally approved:
If, after issuing the COA, the MWS surveyor
notes any non-compliance with the basis on which the COA approval
was provided or with any recommendation, intended to be completed after the issue of the COA, the attending
MWS surveyor shall issue a document of non-compliance formally identifying how the terms, conditions and any recommendations of the COA have been contravened. In such circumstances, subject to confidentiality undertakings of the MWS company, the Lead Underwriter is to be informed of this and the surrounding circumstances at the first opportunity. In all cases the MWS company
must ensure that the Assured’s
representative is formally made aware of the situation
(in writing).
The following CoA’s are provided
as an example of the type of content
and format expected for principle categories of CoA.
Document reviews Comments
TRN's
(levels of comments)
Contract Master Document Kick-off
meeting Suitability survey(s) Report Certificate of Monitoring/
award Register (MDR) (recommendations) Approcal (CoA) advisory role
Interim meeting Meetings
(high level
requirements)
Site attendance(s) Site attendance(s) Inspect arrangements
(recommendations)
Trials and testing Accept/reject
(DP/FMEA analysis, winch testing etc.)
Notes:
Procedure for loadouts, sailaways, installations (platform installation, pipelaying, subsea, project
carago, renewables)
1.
All comments, recommendations or higher level
requirements must be closed out before
the CoA is issued. Hence one CoA is issued for each operation
not intermediate stages otherwise
it becomes meaningless.
2. TRN: Technical Review Note or similar depending on MWS company terminology.
These are a list of comments on the documents being reviewed.
Suggested Certificate of Approval
format for a Loadout
MWS Company name:
Project
No:
Certificate No:
UMR No:
Project Title
Loadout of the on the barge by (lifting/skidding/SPMT)
at
This is to Certify
that this office, acting on behalf of (the MWS Client) has reviewed the procedures
for the above
operation in the document(s):
Title:
Doc. No:
Rev. No.
The undersigned has also witnessed
the preparations for the loadout
of the on the barge at in .
The referenced loadout procedure
is satisfactory, and the proposed
loadout is within the stated capacity of the crane/SPMT/equipment to be used and barge.
Subject
to compliance with the stated
procedures and any additional recommendations submitted
by this office the loadout of the onto the barge is hereby approved.
Any alterations in the surveyed
items after the issue of this Certificate of Approval may render this Certificate invalid
unless approved by this office
(prior to commencement of the operation).
This Certificate is issued in accordance with (terms
and conditions, service contract, variation order etc.) dated . It is issued
solely for the purposes
of the proposed operation
and is based upon external
conditions observed
by the undersigned of the hull, machinery
and equipment without removal,
exposure, operating
or testing of parts.
For and on behalf
of: Receipt
of this COA is hereby acknowledged by:
MWS Company name Client
company name
Print surveyor’s name Print name
SOMWS Membership No.: Time:
Date:
Location: (port/town and country)
(Note: Recommendations are to be specific, measurable, achievable, reasonable, clearly listed
and state the time by which the recommendation is to be completed)
1.
2.
3.
4.
5.
6.
Suggested Certificate of Approval
format for a Sailaway
MWS Company name:
Project
No:
Certificate No: UMR No:
Project Title Transportation on the (ships name)
From
To
Of the Project Cargo:
This is to Certify
that this office, acting on behalf of (the MWS Client) has reviewed the procedures for the above operation in the document(s):
Title:
Doc. No:
Rev. No.
The undersigned has also witnessed
the preparations for the voyage
of the (ship’s name) it is generally
fit to undertake the voyage.
No responsibility is accepted
by this office for the way in which the voyage is undertaken following
departure.
Any alterations in the surveyed
items and/or deviations from the approved procedures after the issue
of this Certificate of Approval
may render this Certificate invalid
unless approved by this office (prior
to commencement of the operation).
This Certificate is issued in accordance with (terms
and conditions, service contract, variation order etc.) dated . It is issued
solely for the purposes
of the proposed operation and is based upon external
conditions observed
by the undersigned of the hull, machinery
and equipment without removal,
exposure, operating
or testing of parts. This Certificate shall
not be deemed or considered to be a general
Certificate of Seaworthiness.
For and on behalf
of: Receipt
of this COA is hereby acknowledged by:
MWS Company name Client
company name
Print surveyor’s name Print name
SOMWS Membership No.: Time:
Date:
Location: (port/town and country)
(Note: Recommendations are to be specific, measurable, achievable, reasonable, clearly listed
and state the time by which the recommendation is to be completed)
1.
2.
3.
4.
5.
6.
Suggested Certificate of Approval
format for a Towage
MWS Company name:
Project
No:
Certificate No: UMR No:
Project Title
Towage of the on the barge by the tug(s)
From
To
This is to Certify
that this office, acting on behalf of (the MWS Client) has reviewed the procedures
for the above operation in the document(s):
Title:
Doc. No:
Rev. No.
The undersigned has also witnessed
the preparations for the towage
of the on the barge from to .
Towage by the tug “vessel
name” owned by is hereby approved
based on
* a bollard
pull of tonnes as stated in the Certificate issued by company
name on date
* an estimated realistic bollard
pull of tonnes
* Delete as applicable
and that it is generally
fit to undertake the tow.
No responsibility is accepted
by this office for the way in which the towage is undertaken following
departure.
Any alterations in the surveyed
items and/or deviations from the approved procedures after the issue
of this Certificate of Approval
may render this Certificate invalid
unless approved by this office (prior
to commencement of the operation).
This Certificate is issued in accordance with (terms
and conditions, service contract, variation order etc.) dated . It is issued
solely for the purposes
of the proposed operation and is based upon external
conditions observed
by the undersigned of the hull, machinery
and equipment without removal,
exposure, operating
or testing of parts. This Certificate shall
not be deemed or considered to be a general
Certificate of Seaworthiness.
For and on behalf
of: Receipt
of this COA is hereby acknowledged by:
MWS Company name Client
company name
Print surveyor’s name Print name
SOMWS Membership No.: Time:
Date:
Location: (port/town and country)
Recommendations:
(Note: Recommendations are to be specific, measurable, achievable, reasonable, clearly listed
and state the time by which the recommendation is to be completed)
1.
2.
3.
4.
5.
6.
Suggested Certificate of Approval
format for an Offshore Installation
MWS Company name:
Project
No:
Certificate No:
UMR No:
Project Title
Installation of the by (crane vessel/HLV)
at Offshore Wind Farm
This is to Certify
that this office, acting on behalf of (the MWS Client) has reviewed the procedures
for the above operation in the document(s):
Title:
Doc. No:
Rev. No.
The undersigned has also witnessed
the preparations for the installation of the .
The referenced installation procedure is satisfactory and the
proposed installation is within the stated
capacity of the crane/HLV/equipment to be used.
Subject
to compliance with the stated
procedures and any additional recommendations submitted
by this office the installation of the onto the is hereby approved.
Any alterations in the surveyed
items after the issue of this Certificate of Approval may render this Certificate invalid
unless approved by this office
(prior to commencement of the operation).
This Certificate is issued in accordance with (terms
and conditions, service contract, variation order etc.) dated . It is issued
solely for the purposes of the proposed operation
and is based upon external
conditions observed
by the undersigned of the hull, machinery
and equipment without removal,
exposure, operating
or testing of parts.
For and on behalf
of: Receipt
of this COA is hereby acknowledged by:
MWS Company name Client
company name
Print surveyor’s name Print name
SOMWS Membership No.: Time:
Date:
Location: (port/town and country)
Append
Recommendations and Checklist
to each COA referring to the unique number
of the Certificate of Approval on each page so that the documents can be associated with each other.
Recommendations:
(Note: Recommendations are to be specific, measureable, achievable, reasonable, clearly listed
and state the time by which the recommendation is to be completed)
1.
2.
3.
4.
5.
6.
Suggested Certificate of Non-compliance
MWS Company name:
Project
No:
Certificate No:
UMR No:
Project Title
Details of activity copied
from the COA affected by this note of non-compliance.
On day
of , , a Certificate of Approval
(Certificate Number
), approving the activity or procedure
subject to compliance with the Recommendations, was issued.
This Certificate of Non-compliance confirms that, on the date(s) and at the time(s) set out below the following
events were observed
which, in the opinion
of the undersigned amount to non-compliance with the Recommendations in the Certificate of Approval or procedures in the following
respects:
1.
Recommendation
( ). (Insert full details
with dates, times, evidence relied
on, photographs etc, emails etc.)
2.
Provisions of (procedures) not complied
with. (Insert full details with dates, times, evidence relied on, photographs etc., emails etc.)
For and on behalf
of MWS Company
name
Print surveyor’s name
SOMWS Membership No.: Time:
Date: Location: (port/town and country)
Receipt of this Certificate of Non-compliance is hereby
acknowledged
Signed: Print name: Date:
No comments:
Post a Comment