Special Conditions Concerning the Construction of Dams and Water Reservoirs



Endorsement 104
Special Conditions Concerning the Construction of Dams and Water Reservoirs


It is agreed and understood that otherwise subject to the terms, exclusions, provisions and conditions contained in the Policy or endorsed thereon, the Insurers shall not indemnify the Insured in respect of :


-       grouting of soft rock areas and/or other additional safety measures even if their necessity arises only during construction,


-       expenses incurred for dewatering even if the quantities of water originally expected are exceeded substantially,

-       loss or damage due to breakdown of the de-watering system if such breakdown could have been avoided by sufficient stand-by facilities,

-       loss or damage due to subsidence if caused by insufficient compacting,


-       cracks and leakage.


Endosemen 104
Kondisi Khusus Mengenai Konstruksi Bendungan dan Penampungan Air


Dengan ini disetujui dan dipahami bahwa lain daripada yang diatur dalam syarat, pengecualian, ketentuan dan kondisi yang terdapat pada Polis atau yang diendos di dalamnya, Penanggung tidak memberi ganti rugi Tertanggung sehubungan dengan :

-       pemlasteran   daerah berbatu lunak dan/atau tindakan pengamanan tambahan lainnya walaupun keperluan tersebut timbul hanya selama konstruksi,

-       biaya  yang timbul untuk pengurasan walaupun jumlah air yang semula diharapkan melebihi secara substansial,

-       kerugian atau kerusakan karena rusaknya sistem pengurasan jika kerusakan tersebut sudah   dihindari oleh fasilitas siaga yang memadai,

-       kerugian atau kerusakan karena tanah surut jika disebabkan oleh pemadatan yang tidak memadai,

-       retak dan bocor.